Agile methodologies have become a game-changer transforming the way teams collaborate when designing, building and deploying new systems.

Agile development approaches break a project down into contained iterations (often called “sprints”) and emphasise adaptation along the project lifecycle. In recent years, there has been an increased emphasis on iterative Agile approaches to improve project outcomes. Agile approaches aim to reduce risk, increase visibility and quicken business value through continuous and evolving development. The term “Agile” emerged in 2001 and was captured in the Agile Manifesto which describes the four values and twelve principles of Agile Software Development, although iterative programme and change management techniques preceded that document for decades.

Key differences between Waterfall and Agile approaches:

Sample Timeline: Global Template/Pilot Deployment Project

However, from the theory to the reality there is a gap, and in our experience it is not all black or white (Waterfall or Agile). For this reason, we want to share our view on what Agile is about and how it can practically be applied when designing, building and deploying a new solution. The diagram below shows the overall flow of a global template project combined with a pilot deployment, combining activities delivered in a traditional Waterfall way (marked in blue) and activities delivered in an Agile way (marked in green).

Key lessons learnt during the different programme phases

Pre Programme Foundations:

  • Industry and technology functional experts interact with key business and IT stakeholders to define the programme’s ambition, target capabilities, future-state application architecture, and implementation approach as well as create a barebones estimate consistent with the business case. A design authority board is established to take key design decisions and govern the template.

Prepare Phase

  • This phase involves planning and preparing for subsequent phases. This includes developing a project/ programme charter, quality management processes, a master plan, pilot selection, an integrated work plan, and a deliverables log. During this phase, the organisation structure is established, the tool strategy is developed, and resources are assigned.

Explore Phase: Provides Backlog Structure and Sprint Plans

Sprint 0.1 – Backlog Structure:

  • During this sprint, workshops are conducted to structure the business processes, articulate options for key design decisions, define enterprise structure elements, and create an initial data model. The controls team identifies L3 processes for which controls will be needed.

Sprint 0.2 – Fit-to-Standard Demos, Gaps:

  • A fit-gap approach is used to determine if gaps to the standard solution exist. Approved developments to fill gaps are captured in development user stories with acceptance criteria.

Sprint 0.3 – Velocity Capacity/Estimation, Key Design Decision Closure:

  • During this sprint, workshops are conducted to structure the business processes, articulate options for key design decisions, define enterprise structure elements, and create an initial data model. The controls team identifies L3 processes for which controls will be needed.

Sprint 0.4 – Sprint Plans and Agile Tools Trained:

  • Key process, data, and developments are plotted on a product roadmap which is used to manage expectations of stakeholders. Only backlog items that have met definition of ready (DoR) criteria, e.g., closed key design decisions, resource availability confirmation, are included in the sprint backlog.

In addition, approaches to harmonise and cleanse data, to document configuration settings at the appropriate structural level, to writing lean specifications for developments, to testing, to identifying change impacts, and to defining the end-user training curriculum are part of the Explore Phase.

Design/Build Phase (and Test Sprints)

Design/Build/Unit Test Sprints

  • These sprints involve design and configuration of L3 processes as well as data design, mapping, loads, and reconciliation. Lean specifications are written approved developments and reviewed in handshake meetings with developers. Sprints are sequenced so that org unit, general configuration settings, and foundational data design are completed first, before design/build/unit testing of standard processes and developments begin. A standard set of tasks will be leveraged across teams to manage sprint flow and to track progress.
  • Enabling teamwork, such as controls, security roles, training curriculum, and change impact action plans are completed in lockstep with process and system object development work. Once processes and data load sequences have been unit tested, they are pre-integration tested using the unit tested security roles.
  • The sprint teams showcase solution increments to product owners as part of a solution review. After solution review, documentation of confirmed solution components is completed. Solution reviews focus on high value work items. Fit-to-standard items are only checked for completion

Pilot Localization Sprints

After completion of pilot site readiness check in previous phase, onboard pilot team.

Run workshops to select template components relevant to sites, confirm localization solutions. Submit any gaps to the design authority.

Build/unit test relevant template components and localizations. Derive security roles. Include pilot site components in pre-integration testing.

Test and Deploy Phases

Test

  • Tests drafted during the Build pre-integration test cycles are formally executed in a formal test environment after a full data load.
  • Integration testing is performed by the core project team, whereas user acceptance testing is performed with a representative set of users from the pilot deployment sites. Critical defects are resolved before proceeding to the Deploy Phase.

Deploy and Hypercare

  • During the cutover stage, the project team delivers the solution to the end users. This involves end-user training, a cutover dress rehearsal, deploying the solution to the production environment, migrating/reconciling data, and redirecting interfaces before conducting business operations in the production system.
  • Production support is provided, system transactions are monitored, support is transitioned to the production support organisation, and the project is closed.
  • In our experience, agile ways of working are most applicable to the Explore and Build phases, when the MVP is defined followed by a series of design/build/unit test sprints during the Build.
  • Transform ERP can help you to find the right Agile balance in your programme with the aim to increase solution acceptance, minimise rework and transfer knowledge to the wider business colleagues from early stages.