global auto manufacturer

Driving a global auto manufacturer SAP S/4HANA programme delivery towards Go Live realisation

Client and context

British multinational automobile manufacturer which produces luxury vehicles and SUVs, designing, developing, manufacturing and selling vehicles.

The client started an SAP S/4HANA and EWM transformation programme to implement the new solutions across all their manufacturing plants
globally, replacing SAP ECC, WM and other systems. The programme was not progressing as expected due to scope creep and additional
customisation out of control. After 2 years of unsuccessful attempts to Go Live with the first manufacturing plant, we were engaged with the SI to recover delivery control, drive delivery to complete Build and System Integration Test (SIT) while supporting the client to complete User Acceptance
Test (UAT) and prepare for Cutover.

global auto manufacturer

Solution

SAP S/4HANA and EWM rollout across the following areas:

  • Order to Cash
  • Record to Report
  • Procure to Pay
  • Supply Chain
  • Production Planning
  • Warehouse Management (SAP EWM)
  • Quality Management
  • Plant Maintenance
  • Transport Management

The difference we made

Business engagement

Finalisation of a global template to be deployed across all countries manufacturing plants and warehouses.

Realisation

Realisation of the first manufacturing plant Go Live in 9 months, after failed attempts to Go Live during the previous 2 years.

SI partner management

SI partner management (mostly off-shore resources) to ensure Build and Configuration were completed on-time, as well as ensuring a high-quality System Integration Test (SIT) was executed.

Processes alignment

The following best practices were applied to bring the programme back on track towards Go Live realisation:

  • New Change Control process to scrutinise and challenge potential new requirements, assessing the value of potential new requirements vs their cost.
  • New Change Request process to improve change Requests management and tracking, as well as anticipating and discussing further needs/ future Change Requests.
  • Alignment of System Integration Test (SIT) with user Acceptance Test (UAT): to ensure the SI SIT scenarios were covering the processes that were going to be UAT tested by the business
    testers.
  • Involvement of all relevant SI stakeholders in the Cutover : plan preparation, dry run and final execution, including non-SAP teams managing other systems interfaced with SAP.